Start-up consent for Tor II

Tor-II-saken.png

9/30/2020 The licensees in the Tor Unit in the southern North Sea have secured consent to start up the Tor II facilities.

The Tor field was proven in 1970 and was in production from 1978 to 2015, when it was shut down.

In the summer of 2019, the licensees submitted a plan for development and operation (PDO) for a new development of the field, called Tor II. The plan was approved by the Ministry of Petroleum and Energy in the autumn of 2019.

The Norwegian Petroleum Directorate has now granted consent for start-up of the Tor II facilities from 1 November 2020.

“Tor is the first field on the Norwegian shelf with a complete redevelopment, receiving consent to start up after having been shut down. We are satisfied that the licensees have found solutions for even better utilisation of the resources in the Tor field,” says Arvid Østhus, the NPD’s assistant director of development and operations – North Sea.

Tor II comprises two new subsea templates to be installed on the Tor field and tied in to Ekofisk, about 13 kilometres away. Eight new production wells will be drilled. The recoverable reserves were estimated at 10 million standard cubic metres of oil equivalent (Sm3) in the PDO.

Operator ConocoPhillips plans start-up in the fourth quarter of 2020, in line with the description in the PDO.

“Tor II shows that shut down fields can create significant values if they are redeveloped. We have produced oil and gas on the NCS for nearly 50 years, and the industry has undergone enormous development through this period. That’s why it’s so great that fields once shut down because they were not profitable can become profitable again today,” says Østhus.

 

Contact
postboks@sodir.no

Tel: +47 51 87 60 00

Updated: 2/10/2025

Latest news

Oil discovery and dry well in the North Sea (31/4-A-23 F and 31/4-A-23 G)
5/28/2025 OKEA and the licensees in production licence 055 have discovered oil along the eastern flank of the Brage field.
Drilling permit for wellbore 35/11-31 S
5/23/2025 The Norwegian Offshore Directorate has granted Equinor Energy AS drilling permit for wellbore 35/11-31 S in production licence 090.
Drilling permit for wellbore 15/5-8 S and 15/5-8 A
5/22/2025 The Norwegian Offshore Directorate has granted Equinor Energy AS drilling permit for wellbore 15/5-8 S and 15/5-8 A in production licence 1140.
Production figures April 2025
5/20/2025 Preliminary production figures for April 2025 show an average daily production of 2 030 000 barrels of oil, NGL and condensate.
Oil discovery in the Norwegian Sea (6507/5-13 S and 6507/5-13 A)
5/20/2025 Aker BP ASA and its partners have made an oil discovery in the so-called E prospect near the Skarv field.
Drilling permit for wellbore 6406/11-2 S
5/19/2025 The Norwegian Offshore Directorate has granted Vår Energi ASA drilling permit for wellbore 6406/11-2 S in production licence 586.
Drilling permit for wellbore 7220/5-4
5/16/2025 The Norwegian Offshore Directorate has granted Equinor Energy AS drilling permit for wellbore 7220/5-4 in production licence 532.
Seminar on deep-sea data on the NCS
5/15/2025 We are organising a seminar on seabed minerals, focusing on deep-sea data that has been collected, and how this data enhances our understanding of biology and geology in the deep sea on the Norwegian continental shelf (NCS).
The wells 32/7-1 and 32/4-4 proved suitable properties for injection and storage of CO2
5/14/2025 Equinor Low Carbon Solutions (Equinor) has drilled two appraisal wells which indicate that the reservoir is suitable for injection and storage of carbon dioxide (CO2).
Drilling permit for wellbore 25/1-14 A, 25/1-14 B and 25/1-14 C
5/13/2025 The Norwegian Offshore Directorate has granted Aker BP ASA drilling permit for wellbore 25/1-14 A, 25/1-14 B and 25/1-14 C in production licence 873 B.