Cost development

16/01/2012 The Norwegian petroleum activities are experiencing a period of strong growth in activities and high investment levels. This is positive; however, such a development also poses challenges as regards capacity and the companies’ ability to implement planned projects.

Investments including exploration are expected to rise from just under NOK 150 billion in 2011 to about NOK 170 billion in 2012, cf. Figure 1. A further moderate increase is expected toward 2016. If exploration activity is excluded, investments during the period 2010-2012 will grow by more than 40 per cent.

Exploration costs in 2012 are estimated at about NOK 30 billion, which is approximately the same level as estimated in the previous forecast.

 

 Development in investments on the Norwegian shelf – forecast from and including 2011.

Figure 1: Development in investments on the Norwegian shelf – forecast from and including 2011.

 

In 2010, investments declined for the first time since 2002, from a level of a scant NOK 150 billion in 2009. One of the contributing causes of the decline was the drop in oil prices in the wake of the financial crisis in 2008. For the next few years, a similar trend of increasing investments as from before 2010 is expected to continue.

Investments undertaken in 2011 ended a little lower than expected at the previous year-end. The Norwegian Petroleum Directorate’s new forecast for the period from and including 2012 shows an increase in investments compared with the previous forecast, cf. Figure 2.

 

Forecast to the revised national budget RNB2012, compared with the previous forecast

Figure 2: Forecast to the revised national budget RNB2012, compared with the previous forecast

 

A number of development projects contribute to the strong growth in investments during the period up to 2016. Figure 3 illustrates the development in investments for a selection of such projects. These contribute to an increase in investments of about NOK 45 billion from 2010 to 2012.

 

 Increase in investments 2010-2012 for a selection of development projects

Figure 3: Increase in investments 2010-2012 for a selection of development projects

 

During the period 2010-2012, it is particularly investments in new facilities that will rise, both new fixed- and floating facilities, and subsea facilities. Operational investments in producing fields also contribute to the increase. Up to 2016, the increase in overall investments largely relates to higher investments in development of discoveries and new projects on fields currently in operation. All in all, this will help maintain record-high investment levels on the Norwegian shelf in the next few years.

Most of the investments in the NPD’s forecasts linked to the Skrugard, Havis and Aldous/Avaldsnes discoveries will come after 2016, and will thus contribute to maintaining continued high investment levels up to 2020.


The challenge of a high activity level

The development in the activity level represents a number of capacity challenges, both in connection with studying and maturing projects, project implementation for operating companies and deliveries of goods and services from the supplier industry. This is the case despite the fact that some of the investments will be linked to activity carried out abroad.

Access to drilling rigs is a crucial bottleneck. When available information about new rigs is compared with planned drilling activity, it is evident that the industry faces a considerable challenge in obtaining sufficient rig capacity for drilling and well maintenance on fields, as well as for new developments and exploration. Compared with the operating companies’ project reporting of future investments, the NPD expects a substantial delay in projects. Such a delay has been used as a basis for the forecast in Figure 1.

The investment forecast is based on the oil companies’ oil price expectations. However, the international financial situation is uncertain. A sharp and prolonged decline in the price of oil could have a major impact on investments. However, for 2012, and to some extent also for 2013, the investments are largely linked to projects that have already been approved and initiated.


Operating costs

Operating costs are expected to amount to more than NOK 60 billion in 2012, and then rise moderately in the subsequent years due to development of discoveries.


Overall costs

Development in overall costs in the petroleum activities is illustrated in Figure 4.

 

Forecast for development of the overall cost level

Figure 4: Forecast for development of the overall cost level

 

The price development for goods and services will determine the overall development in the cost level, measured in current NOK. The effect of various price increase scenarios is illustrated in Figure 5.

 

Development of cost level under various cost growth assumptions

Figure 5: Development of cost level under various cost growth assumptions

 

Updated: 16/01/2012

Latest news

Announcement of awards in predefined areas (APA) 2024
08/05/2024 The Ministry of Energy announced APA 2024 on 8 May 2024, encompassing the predefined areas with blocks in the Norwegian Sea, Norwegian Sea and Barents Sea.
Drilling permission for the wells 7324/6-2 and 7324/8-4
06/05/2024 The Norwegian Offshore Directorate has granted Aker BP ASA drilling permit for the wells 7324/6-2 and 7324/8-4 in production license 1170, cf. Section 13 of the Resource Management Regulations.
Eight companies have applied for CO2 storage acreage
30/04/2024 The Norwegian Ministry of Energy has received applications from eight companies in connection with the announcement of two areas in the North Sea for potential storage of CO2 on the Norwegian shelf.
Invitation to nominate blocks for mineral activities on the seabed
29/04/2024 In a letter of 29 April, the Norwegian Offshore Directorate invited players to nominate blocks in connection with the first licensing round for mineral activities on the seabed.
Drilling permission for wells 35/10-14 S and 35/10-14 A
29/04/2024 The Norwegian Offshore Directorate has granted Equinor Energy AS drilling permit for wells 35/10-14 S and 35/10-14 A in production license 1185, cf. Section 13 of the Resource Management Regulations.
Well for data acquisition on Wisting
22/04/2024 Equinor has completed an appraisal well (7324/7-4) on the Wisting discovery in the Barents Sea. The objective was to acquire data on the reservoir and cap rock, for use in ongoing evaluation and development of the discovery.
Production figures March 2024
19/04/2024 Preliminary production figures for March 2024 show an average daily production of 2 086 000 barrels of oil, NGL and condensate.
Norwegian Offshore Directorate publishes new deep sea data
17/04/2024 In June 2022, the Norwegian Offshore Directorate published data collected up to 2022. The Directorate is now releasing deep sea data gathered from 2022 to 2024.
The future in the Barents Sea is here now
17/04/2024 The Johan Castberg ship will soon be heading north. With the ship in place, the plan is to have three producing fields in the Barents Sea by the end of the year.
Oil discovery in the North Sea
17/04/2024 Vår Energi has made an oil discovery in "Ringhorne Nord" (wells 25/8-23 S and 25/8-23 A & B), north of the Ringhorne Øst field, 200 kilometres northwest of Stavanger.