29/08/2016 The price tag for developing a field on the Norwegian shelf has declined by an average of more than 40 per cent since the autumn of 2014, according to the NPD's analysis of eight planned developments that are approaching start-up.

The decline is a result of a combination of simpler development concepts and more efficient drilling. Lower prices for work and equipment are also a contributing factor.

The investment estimates for the Utgard, Oda, Zidane, Trestakk, Snilehorn, Johan Castberg, Snorre Expansion and Johan Sverdrup Phase 2 projects have fallen from about NOK 270 to 150 billion, according to the operating companies' own calculations. The downward adjustments have been made in connection with various decision phases in project implementation.

"This is a significant and very welcome reduction", says the NPD's Director of development and operations, Ingrid Sølvberg.

"The oil companies and the supplier industry have made a tremendous effort in streamlining the activities, and now we can see that these measures are working."

The biggest savings on these eight projects are a result of altered development solutions. The second largest reduction is within drilling and wells, which on average accounts for around 30 per cent of the overall field development costs. This is due to the decline in rental rates for drilling rigs, and also that the companies are planning wells that can be drilled faster. The actual drilling operation has also become more efficient, so that the price per metre of well will be much lower than before.

Investments in pipelines and cables are also expected to decline significantly. This is a result of falling prices for materials, and choosing different routes. Simplified development solutions and less costly materials will yield more reasonably priced modifications and adaptations of facilities where the oil and gas from new developments will be taken in and processed.

Despite the positive development in the cost scenario, Sølvberg cautions against short-term savings at the expense of long-term value creation on the shelf. She also warns against cutting staff in important technical environments, as it could impair the capacity for innovation and the ability to find smart solutions.

The NPD has noted tendencies where companies prioritise minimum investment in the development phase, but that could limit subsequent upgrades of the facilities, or make them more expensive.

"We must not put ourselves in a situation where cost cuts reduce the future flexibility on the fields, or have a detrimental impact on our ability and willingness to use technology that can provide better and more efficient resource management," says the development director.

Updated: 29/08/2016

Latest news

Announcement of awards in predefined areas (APA) 2024
08/05/2024 The Ministry of Energy announced APA 2024 on 8 May 2024, encompassing the predefined areas with blocks in the Norwegian Sea, Norwegian Sea and Barents Sea.
Drilling permission for the wells 7324/6-2 and 7324/8-4
06/05/2024 The Norwegian Offshore Directorate has granted Aker BP ASA drilling permit for the wells 7324/6-2 and 7324/8-4 in production license 1170, cf. Section 13 of the Resource Management Regulations.
Eight companies have applied for CO2 storage acreage
30/04/2024 The Norwegian Ministry of Energy has received applications from eight companies in connection with the announcement of two areas in the North Sea for potential storage of CO2 on the Norwegian shelf.
Invitation to nominate blocks for mineral activities on the seabed
29/04/2024 In a letter of 29 April, the Norwegian Offshore Directorate invited players to nominate blocks in connection with the first licensing round for mineral activities on the seabed.
Drilling permission for wells 35/10-14 S and 35/10-14 A
29/04/2024 The Norwegian Offshore Directorate has granted Equinor Energy AS drilling permit for wells 35/10-14 S and 35/10-14 A in production license 1185, cf. Section 13 of the Resource Management Regulations.
Well for data acquisition on Wisting
22/04/2024 Equinor has completed an appraisal well (7324/7-4) on the Wisting discovery in the Barents Sea. The objective was to acquire data on the reservoir and cap rock, for use in ongoing evaluation and development of the discovery.
Production figures March 2024
19/04/2024 Preliminary production figures for March 2024 show an average daily production of 2 086 000 barrels of oil, NGL and condensate.
Norwegian Offshore Directorate publishes new deep sea data
17/04/2024 In June 2022, the Norwegian Offshore Directorate published data collected up to 2022. The Directorate is now releasing deep sea data gathered from 2022 to 2024.
The future in the Barents Sea is here now
17/04/2024 The Johan Castberg ship will soon be heading north. With the ship in place, the plan is to have three producing fields in the Barents Sea by the end of the year.
Oil discovery in the North Sea
17/04/2024 Vår Energi has made an oil discovery in "Ringhorne Nord" (wells 25/8-23 S and 25/8-23 A & B), north of the Ringhorne Øst field, 200 kilometres northwest of Stavanger.