8/14/2019 The Norwegian Petroleum Directorate has granted its consent to start-up of the Utgard field in the North Sea.

Operator Equinor is planning start-up during autumn 2019.

The field is located on the border with the UK, and the Norwegian share is 62 per cent. Consent for start-up of Utgard is granted to the licensees in production licences 046E and 046F on the Norwegian shelf and in production licence 312 on the UK shelf.

Positive utilisation of capacity

The production will take place from two wells from a subsea template linked to the Sleipner T process platform with a pipeline and a communications cable. Modifications have also been made on Sleipner T in order to process the wellstream from Utgard.

Investments in the field development total close to NOK 3 billion.

“Utgard contributes to utilise available capacity on Sleipner, which is positive. The project ensures good and cost-effective utilisation of the facilities and the process capacity on Sleipner,” says Tove Francke, Assistant director for development and operations, North Sea south.

“We expect Utgard will create value both for the Norwegian society and for the Utgard and Sleipner licensees,” Francke adds.

Equinor estimates the expected total sales volume at 1.71 million Sm³ condensate, 2.73 billion Sm³ gas and 0.56 million tonnes NGL.

The Utgard field was proven in 1982 and the PDO was approved in early 2017.

 

 

Updated: 8/16/2019

Latest news

New CCS guidelines
11/3/2025 The Norwegian Offshore Directorate has drawn up guidelines explaining how to fulfil the requirements in Section 26 of the Regulations relating to documentation in connection with storage of CO2 on the Norwegian continental shelf.
New report about power from shore
10/29/2025 Power from shore as replacement for gas turbines has been the most important abatement to reduce greenhouse gases emissions offshore.
Drilling permit for wellbore 7018/5-2
10/29/2025 The Norwegian Offshore Directorate has granted Equinor Energy AS drilling permit for wellbore 7018/5-2 in production licence 1236.
Drilling permit for wellbore 25/8-C-23 D
10/24/2025 The Norwegian Offshore Directorate has granted Vår Energi ASA drilling permit for wellbore 25/8-C-23 D in production licence 027.
Production figures September 2025
10/21/2025 Preliminary production figures for September 2025 show an average daily production of 1 991 000 barrels of oil, NGL and condensate.
Public consultation – proposed changes to two regulations
10/2/2025 The Norwegian Offshore Directorate is submitting proposed changes to the Resource Management Regulations and the Regulations relating to documentation in connection with storage of CO2 on the shelf for public consultation.
Drilling permit for wellbore 35/8-8 S
10/2/2025 The Norwegian Offshore Directorate has granted Harbour Energy Norge AS drilling permit for wellbore 35/8-8 S in production licence 248 LS og 248 B.
Popular tours of the Geobank during the Ulltra festival – celebrating the future
9/26/2025 At the end of September, the Norwegian Offshore Directorate participated in a brand-new festival at Ullandhaug - Ulltra 2025. Registered visitors had the opportunity to take part in a guided tour of the Geobank in our offices. 
Seabed data from this summer’s cruise now available for order
9/26/2025 Orders can now be placed for data from this summer’s cruise in the Lofoten Basin (east of the Mohns Ridge) in the Norwegian Sea and the southwestern part of the Knipovich Ridge in the Greenland Sea.
Green light for export via gas pipeline from Troll B
9/25/2025 The Norwegian Offshore Directorate has granted consent for start-up of a tie-in from the Troll B platform to the Kvitebjørn gas export line.