Received PDO for Breidablikk

breidablikk.jpg

Breidablikk will be developed with four subsea templates tied into the Grane facility. (illustration: Equinor) 

9/28/2020 The authorities have received a plan for development and operation (PDO) for the Breidablikk oil field in the North Sea. Equinor and its partners are planning start-up in 2024.

Breidablikk (previously called Grand) is located northeast of the Grane field, approx. 185 kilometres west of Haugesund. The total recoverable reserves from Breidablikk are estimated at about 30 million standard cubic metres (Sm3) of oil. This equates to 200 million barrels. 

The field will be developed with four subsea templates, each with six slots. The templates will be tied into the Grane facility. 

The plan calls for 23 production wells on the field. The oil will be processed and exported via Grane to the Sture terminal in Hordaland county.

According to the operator, investments for the Breidablikk development will total around NOK 18,6 billion.  

“This is an important project in terms of improving recovery from the Grane area, and it is also a good utilisation of existing infrastructure,” says Arvid Østhus, the NPD’s assistant director for development and operations – North Sea.  

The Breidablikk field consists of the 25/11-27 discovery (F structure) and the 25/8-4 discovery (D structure). 

The owners are Equinor (operator), Petoro, Vår Energi and ConocoPhilips Skandinavia.

Read more about the project here (in Norwegian only).

Contact
Bjørn Rasen

Tel: +47 51 87 60 00

Updated: 9/28/2020

Latest news

New report about power from shore
10/29/2025 Power from shore as replacement for gas turbines has been the most important abatement to reduce greenhouse gases emissions offshore.
Drilling permit for wellbore 7018/5-2
10/29/2025 The Norwegian Offshore Directorate has granted Equinor Energy AS drilling permit for wellbore 7018/5-2 in production licence 1236.
Drilling permit for wellbore 25/8-C-23 D
10/24/2025 The Norwegian Offshore Directorate has granted Vår Energi ASA drilling permit for wellbore 25/8-C-23 D in production licence 027.
Production figures September 2025
10/21/2025 Preliminary production figures for September 2025 show an average daily production of 1 991 000 barrels of oil, NGL and condensate.
Public consultation – proposed changes to two regulations
10/2/2025 The Norwegian Offshore Directorate is submitting proposed changes to the Resource Management Regulations and the Regulations relating to documentation in connection with storage of CO2 on the shelf for public consultation.
Drilling permit for wellbore 35/8-8 S
10/2/2025 The Norwegian Offshore Directorate has granted Harbour Energy Norge AS drilling permit for wellbore 35/8-8 S in production licence 248 LS og 248 B.
Popular tours of the Geobank during the Ulltra festival – celebrating the future
9/26/2025 At the end of September, the Norwegian Offshore Directorate participated in a brand-new festival at Ullandhaug - Ulltra 2025. Registered visitors had the opportunity to take part in a guided tour of the Geobank in our offices. 
Seabed data from this summer’s cruise now available for order
9/26/2025 Orders can now be placed for data from this summer’s cruise in the Lofoten Basin (east of the Mohns Ridge) in the Norwegian Sea and the southwestern part of the Knipovich Ridge in the Greenland Sea.
Green light for export via gas pipeline from Troll B
9/25/2025 The Norwegian Offshore Directorate has granted consent for start-up of a tie-in from the Troll B platform to the Kvitebjørn gas export line.
Production figures August 2025
9/23/2025 Preliminary production figures for August 2025 show an average daily production of 2 124 000 barrels of oil, NGL and condensate.