Planning redevelopment of the Hod field

Hod_B_final_large.jpg

Illustration of the Hod field, Aker BP.

6/24/2020 On behalf of the licensees, operator Aker BP has submitted a Plan for Development and Operation (PDO) for a redevelopment of the Hod field in the Valhall area in the North Sea.

The field was in production via a dedicated unstaffed wellhead platform, remote-controlled from Valhall, from 1990 until it was shut down in 2012. There has also been limited production from the Hod field via the Valhall Flank South platform.

When the Hod wellhead platform was shut down, just 20 per cent of the resources in place had been produced. The shutdown platform will be removed in accordance with a previously approved cessation plan.

The field will be redeveloped by installing a new wellhead platform tied in to the Valhall field centre. The recoverable reserves are estimated at about 6.4 MSm3 oil equivalents.

"Very gratifying"

The plan is to resume production at the beginning of 2022. The total investment costs for the redevelopment are estimated at NOK 5.7 billion.

“It is very gratifying that the companies have found it profitable to redevelop Hod to increase recovery of the remaining resources,” says Arvid Østhus, assistant director in Development and operations.

 

Contact
postboks@sodir.no

Tel: +47 51 87 60 00

Updated: 2/10/2025

Latest news

Public consultation – proposed changes to two regulations
10/2/2025 The Norwegian Offshore Directorate is submitting proposed changes to the Resource Management Regulations and the Regulations relating to documentation in connection with storage of CO2 on the shelf for public consultation.
Drilling permit for wellbore 35/8-8 S
10/2/2025 The Norwegian Offshore Directorate has granted Harbour Energy Norge AS drilling permit for wellbore 35/8-8 S in production licence 248 LS og 248 B.
Popular tours of the Geobank during the Ulltra festival – celebrating the future
9/26/2025 At the end of September, the Norwegian Offshore Directorate participated in a brand-new festival at Ullandhaug - Ulltra 2025. Registered visitors had the opportunity to take part in a guided tour of the Geobank in our offices. 
Seabed data from this summer’s cruise now available for order
9/26/2025 Orders can now be placed for data from this summer’s cruise in the Lofoten Basin (east of the Mohns Ridge) in the Norwegian Sea and the southwestern part of the Knipovich Ridge in the Greenland Sea.
Green light for export via gas pipeline from Troll B
9/25/2025 The Norwegian Offshore Directorate has granted consent for start-up of a tie-in from the Troll B platform to the Kvitebjørn gas export line.
Production figures August 2025
9/23/2025 Preliminary production figures for August 2025 show an average daily production of 2 124 000 barrels of oil, NGL and condensate.
Dry well in the North Sea (34/8-20 S)
9/19/2025 Equinor and its partners Vår Energi and Aker BP have drilled a dry well about 130 kilometres west of Florø.
Drilling permit for wellbore 34/4-19 S
9/15/2025 The Norwegian Offshore Directorate has granted Equinor Energy AS drilling permit for wellbore 34/4-19 S in production licence 057.
Drilling permit for wellbore 34/6-9 S
9/15/2025 The Norwegian Offshore Directorate has granted Equinor Energy AS drilling permit for wellbore 34/6-9 S in production licence 554.
Oil discovery in the North Sea (31/4-A-15 B)
9/11/2025 OKEA and its partners have made an oil discovery near the Brage field.