Consent to start up Troll phase 3

Equinor-Oyvind-Gravaas-Even-Kleppe-Troll3

Photo: Equinor/Øyvind Gravås and Even Kleppe.

02/07/2021 Licensees in Troll Nord in the North Sea have secured consent to start up facilities and modifications associated with the Troll phase 3 project.

The PDO for Troll phase 3 was approved in December 2018. The project is a further development of the Troll field and will produce the gas from Troll Vest.

The development solution chosen by the operator Equinor and its partners comprises two subsea templates with eight gas wells tied into the Troll A platform. The wellstream from these wells is routed to Troll A through a new 36-inch pipeline, for further compression and export via existing infrastructure.

Recoverable reserves from Troll phase 3, mainly gas, are estimated at about 2.2 billion barrels (350 million standard cubic metres) of oil equivalent.

Major supplier of gas to the continent

"Troll is a giant on the Norwegian shelf. The field supplies as much as 7 per cent of Europe’s daily demand for gas, and Troll phase 3 will help maintain a high level of production for a long time to come," says Wenche Tjelta Johansen, Leader of Licence management.

The licensees have invested just over 8 billion kroner in Troll phase 3, and the plan is for it to produce for at least 30 years. Troll phase 3 was originally scheduled to come on stream this spring, but start-up was postponed until the autumn due to the Covid-19 restrictions.

Troll was proven in 1979, and the original plan for development and operation (PDO) was approved in 1986. The plan was updated in 1990 in order to move the gas processing to the Kollsnes terminal. The field came on stream in 1995.

Developed in phases

Troll was developed in phases, with gas extraction from Troll Øst in phase 1 and oil from Troll Vest in phase 2. Troll phase 1 was developed with Troll A, which is a fixed foundation wellhead and compression installation with a concrete substructure. Troll A receives power from shore. Gas compression capacity was expanded on Troll A in 2004/2005 and again in 2015.

Troll phase 2 was developed with Troll B, which is a floating living quarters and production facility in concrete, and Troll C, which is a semi-submersible living quarters and production facility in steel.

The oil in Troll Vest is produced from multiple subsea templates tied into Troll B and Troll C via pipelines. Production from the Troll C installation started in 1999. Troll C is also used for production from Fram, Fram H-Nord and Byrding. Several amended development plans (PDOs) were approved in connection with installing multiple subsea templates on Troll Vest.

Illustration showing Troll phase 3 expansion

Illustration of Troll phase 3: Equinor.

 

Contact

Ola Anders Skauby

Director Communication, public affairs and emergency response

Tel: +47 905 98 519

Updated: 02/07/2021

Latest news

Announcement of awards in predefined areas (APA) 2024
08/05/2024 The Ministry of Energy announced APA 2024 on 8 May 2024, encompassing the predefined areas with blocks in the Norwegian Sea, Norwegian Sea and Barents Sea.
Drilling permission for the wells 7324/6-2 and 7324/8-4
06/05/2024 The Norwegian Offshore Directorate has granted Aker BP ASA drilling permit for the wells 7324/6-2 and 7324/8-4 in production license 1170, cf. Section 13 of the Resource Management Regulations.
Eight companies have applied for CO2 storage acreage
30/04/2024 The Norwegian Ministry of Energy has received applications from eight companies in connection with the announcement of two areas in the North Sea for potential storage of CO2 on the Norwegian shelf.
Invitation to nominate blocks for mineral activities on the seabed
29/04/2024 In a letter of 29 April, the Norwegian Offshore Directorate invited players to nominate blocks in connection with the first licensing round for mineral activities on the seabed.
Drilling permission for wells 35/10-14 S and 35/10-14 A
29/04/2024 The Norwegian Offshore Directorate has granted Equinor Energy AS drilling permit for wells 35/10-14 S and 35/10-14 A in production license 1185, cf. Section 13 of the Resource Management Regulations.
Well for data acquisition on Wisting
22/04/2024 Equinor has completed an appraisal well (7324/7-4) on the Wisting discovery in the Barents Sea. The objective was to acquire data on the reservoir and cap rock, for use in ongoing evaluation and development of the discovery.
Production figures March 2024
19/04/2024 Preliminary production figures for March 2024 show an average daily production of 2 086 000 barrels of oil, NGL and condensate.
Norwegian Offshore Directorate publishes new deep sea data
17/04/2024 In June 2022, the Norwegian Offshore Directorate published data collected up to 2022. The Directorate is now releasing deep sea data gathered from 2022 to 2024.
The future in the Barents Sea is here now
17/04/2024 The Johan Castberg ship will soon be heading north. With the ship in place, the plan is to have three producing fields in the Barents Sea by the end of the year.
Oil discovery in the North Sea
17/04/2024 Vår Energi has made an oil discovery in "Ringhorne Nord" (wells 25/8-23 S and 25/8-23 A & B), north of the Ringhorne Øst field, 200 kilometres northwest of Stavanger.