Green light for Hod B

Hod_B_1920x1080-AkerBP.jpg

Hod B in the North Sea will soon come on stream, thanks to an unmanned facility remote-controlled from the Valhall field. (illustration: Aker BP)

4/20/2022 The authorities have granted Aker BP consent to start up the Hod B facility in the North Sea.

The operator has embarked upon the start-up process. Aker BP and the other licensees have invested nearly NOK 6.2 billion in the Hod B development.

The reserves are estimated at 6.3 million standard cubic metres of oil, which is equivalent to 40 million barrels. The field is expected to produce until 2049.

Can blaze a trail for other fields

“There are major remaining recoverable volumes in several fields on the NCS that have already been shut down. The experience gained and lessons learned from the redevelopment of Hod can blaze a trail for the development of additional shut down fields, in part through coordinated development with other fields in the area,” says Thomas Mørch, head of Licence Management in the Norwegian Petroleum Directorate.

The Hod field is located in the southern part of the Norwegian sector, 13 kilometres south of the Valhall field. Hod was proven in 1974 and the plan for development and operation (PDO) was approved in 1988. Production started in 1990.

The field has been developed with an unmanned wellhead facility, remotely controlled from Valhall. The plan is to remove the Hod facility in 2025.

A PDO for a new unmanned facility was approved in December 2020. Hod B was installed on the field in July and August 2021.

 

Contact

Ola Anders Skauby

Director Communication, public affairs and emergency response

Tel: +47 905 98 519

Updated: 4/20/2022

Latest news

Looking for the new edition of the continental shelf map?
8/15/2025 The shelf map has now been updated as of July 2025. It shows fields, discoveries, awarded areas, and areas opened for exploration on the Norwegian Continental Shelf (NCS).
Drilling permit for wellbore 2/6-8 S
8/11/2025 The Norwegian Offshore Directorate has granted DNO Norge AS drilling permit for wellbore 2/6-8 S in production licence 1086.
Johan Castberg plays a key role in the Barents Sea
8/8/2025 The Johan Castberg field will be producing oil for many years to come, and new discoveries can be incorporated. The field is important for further development in the Barents Sea.
Production figures June 2025
7/22/2025 Preliminary production figures for June 2025 show an average daily production of 1 854 000 barrels of oil, NGL and condensate.
Gas/condensate discovery in the Norwegian Sea (6406/11-2 S)
7/21/2025 Vår Energi and its partners have made a gas/condensate discovery in the “Vidsyn” prospect.
Dry well in the North Sea (34/6-8 S)
7/17/2025 Equinor and its partners have drilled a dry well in the "Garantiana NV" prospect.
Dry well in the Norwegian Sea (6606/4-1 S)
7/16/2025 OMV and its partners have drilled a dry well in the "Hoffmann" prospect.
Gas discovery near the Johan Castberg field in the Barents Sea - (7220/5-4)
7/10/2025 Equinor Energy AS and its partners have made a gas discovery in the "Skred" prospect.
Drilling permit for wellbore 34/8-20 S and 34/8-20 A
7/9/2025 The Norwegian Offshore Directorate has granted Equinor Energy AS drilling permit for wellbore 34/8-20 S and 34/8-20 A in production licence 554 E.
Drilling permit for wellbore 31/4-A-15 B
6/30/2025 The Norwegian Offshore Directorate has granted OKEA ASA drilling permit for wellbore 31/4-A-15 B in production licence 055.